Contract Work
Below is a summary of upcoming contract packages for work to be done for the Kemper IGCC Project. To be considered for work with Mississippi Power, new suppliers are encouraged to fill out a supplier registration packet using the online Supplier Registration system or by e-mailing Mississippi Power Supply Chain Management. For more information on registering as a supplier, see our Supplier Q&A.
Inquiry package: Electrical Supply Trailer on Site
Area: Plant Site
Description: Supply electrical supplies for project
Type Contract: Unit Price
Approximate Issue Inquiry Date: October 1, 2011
Approximate Start Date: January 1, 2012
Inquiry package: CO2 Capture Pipeline
Area: Transmission Access
Description: Construct CO2 line
Type Contract: Lump Sum
Rev 0 from Engineering: November 11, 2011
Approximate Issue Inquiry Date: December 1, 2011
Approximate Start Date: March 1, 2012
Possible Sub Contracts: Surveying
Supplies/Equipment: Fuel and equipment
Inquiry package: Natural Gas Pipeline
Area: Transmission Access
Description: Install underground gas line form plant site to main gas line 6 Miles
Type Contract: Lump Sum
Rev 0 from Engineering: November 11, 2011
Approximate Issue Inquiry Date: December 1, 2011
Approximate Start Date: March 1, 2012
Possible Sub Contracts: Surveying
Supplies/Equipment: Fuel and equipment
Inquiry package: Landscape Plant Site - Phase 2 Final
Area: Plant Site
Description: Trees, grass, shrubs etc.
Type Contract: Unit Price
Approximate Issue Inquiry Date: December 1, 2013
Approximate Start Date: March 1, 2014
Inquiry package: Final Roadway Paving - Asphalt
Area: Plant Site
Description: Final grading and final asphalt surface
Type Contract: Unit Price
Approximate Issue Inquiry Date: February 1, 2014
Start Date: June 1, 2014