Mississippi Power’s monthly Kemper filing with the Securities and Exchange Commission indicates there was no material change to the estimated cost for the Kemper Project that is subject to the cost cap. As a result, no additional charges to earnings will be recorded in the second quarter of 2014.
“I’ve said before that we are a family and we will get through this together, and these results are proof of our continued commitment to this project,” said CEO Ed Holland. “Our investment in integrated coal gasification and the Kemper project, and our belief that this technology represents the future of coal and energy production have never changed.”
As of June 30, 2014, Mississippi Power’s cost estimate for the plant portion of the Kemper project remains approximately $4.44 billion, net of the DOE grants and excluding the cost cap exceptions. Total project cost is estimated at approximately $5.56 billion.
This summer, Kemper employees successfully reached a pair of significant milestones – successful testing of the combined cycle unit and pressure testing both gasifiers.
“Our employees are committed to bringing this plant online as quickly and safely as possible,” said John Huggins, vice president of Generation Development. “The milestones we reached this summer are a huge accomplishment that every employee should be excited about.”
Certain information contained herein is forward-looking information based on current expectations and plans that involve risks and uncertainties. Forward-looking information includes, among other things, statements concerning the projected cost and schedule for the completion of construction and start-up of the Kemper IGCC. Mississippi Power cautions that there are certain factors that could cause actual results to differ materially from the forward-looking information that has been provided. The reader is cautioned not to put undue reliance on this forward-looking information, which is not a guarantee of future performance and is subject to a number of uncertainties and other factors, many of which are outside the control of Mississippi Power; accordingly, there can be no assurance that such suggested results will be realized. The following factors, in addition to those discussed in Mississippi Power’s Form 10-K for the fiscal year ended December 31, 2013, and subsequent securities filings, could cause actual results to differ materially from management expectations as suggested by such forward-looking information: the impact of recent and future federal and state regulatory changes, as well as changes in application of existing laws and regulations; current and future litigation, regulatory investigations, proceedings, or inquiries; available sources and costs of fuels; state and federal rate regulations and the impact of pending and future rate cases and negotiations, including rate actions relating to fuel and other cost recovery mechanisms; ability to control costs and avoid cost overruns during the development and construction of facilities, which includes the development and construction of generating facilities with designs that have not been finalized or previously constructed, including those risks identified above that have caused and may continue to cause cost increases and/or extensions of the in-service date; ability to construct facilities in accordance with the requirements of permits and licenses to satisfy any operational and environmental performance standards, including any Mississippi PSC requirements and the requirements of tax credits and other incentives, and to integrate facilities into the Southern Company system upon completion of construction; advances in technology; actions related to cost recovery for the Kemper IGCC, including actions relating to proposed securitization, Mississippi PSC approval of Mississippi Power’s proposed rate recovery plan, as ultimately amended, which currently includes the ability to complete the proposed sale of an interest in the Kemper IGCC to South Mississippi Electric Power Association, the ability to utilize bonus depreciation, which currently requires that assets be placed in service in 2014, and satisfaction of requirements to utilize investment tax credits and grants; Mississippi PSC review of the prudence of Kemper IGCC costs; the outcome of any legal or regulatory proceedings regarding the Mississippi PSC’s issuance of the Certificate of Public Convenience and Necessity for the Kemper IGCC, the settlement agreement between Mississippi Power and the Mississippi PSC, the March 2013 rate order, or the State of Mississippi legislation designed to enhance the Mississippi PSC’s authority to facilitate development and construction of baseload generation in the State of Mississippi; and the ability of counterparties of Mississippi Power to make payments as and when due and to perform as required. Mississippi Power expressly disclaims any obligation to update any forward-looking information.